2.Case Analysis
3.Solutions
4.Creative IDEA
Cranberry Grower
99% of the Berries sold were produced by Cooperatives
New techniques
Water Harvesting
High Mechanization
allowed a faster treatment of fruits
Explanation of the RP1’s Main Problems
Incontrollable Overtime Costs
Excessive Waiting Time
(Overtime)
Increasing Growers’ Complaining
Capacity Analysis
Berries Upload to Dump
Average Truck Delivery is 75bbl
Suppose to Take 10minutes to Each Truck.
Each Dumps Capacity
=75(bbl/hr)×6=450(bbl/hr)
Total Dumps Capacity
=450(bbl/hr)×5=2,250(bbl/hr