· Wet Storage Bins : 1200~3200(bbl/hr)
· Total wet berries : app. 19,000
· Arrival of wet berries
: 19,000 bbls * 70%= 13,330 bbls
· Needed Operation time
: 13,330 bbls/600 bbls/hr = 22.2hr
· Wet berries to be processed
: 13,330 bbls/11hr= 1,210 bbls/hr
· Inventory rate of wet berries
: 1,210–600= 610 bbls/hr
· Max inventory
: 610 bbls/hr*11hr= 6,710 bbls
· The time that the truck queue begins
: 3,200 bbls/610 bbls/hr = 5.25hr
◆ Cost analysis
▪Benefits (Overtime saving costs)
- Low-volume period : (6+1+10+8+1) * $3.75 * 5.6(hrs) = $546
→ $546 * 85(days) = $46,410
- High-volume period : (6+1+10+8+1) * $3.75 * 5.6(hrs) = $546
- High-volume period : (9+5+12) * $2.25 * 1.5(overtime rate) * 5.6(hrs) = $491.4
→ ($546 + $491.4) * 21(days) = $21,785.4
- Total : $68,195.4